Reporting overview

EasyBoards® allows to rapidly access to reporting related to Kanban use. Reports are launched from the Reports command available in each board (so from the boards).

The available reports, in alphabetical order, are:

  • Burndown Chart
  • Due Date Performance
  • Flow Efficiency
  • Issues
  • Lead Time
  • Progress view
  • Quality
  • Throughput
  • Velocity
  • Work in Progress

Many reports are generated using statistical information of cards (Commitment Point, Work in Progress, Delivery Point, Working Time, %:, Defective). Statistical information can be viewed in the Statistics form of a card, see Cards details and settings for more details. They are automatically set by the system when a card is moved in lanes, based on lanes settings, see Options form details in Lanes settings. For example, when a card is moved to a lane labelled as "Commitment Point", the card Commitment Point date and time is set accordingly. However, they can also be manually edited in card by board members with the required privilege.

Burndown Chart

This report is the typical burndown chart using by scrum teams. In the x axis the time of the typical scrum sprint is reported and the y axis the remaining story points to be done is plotted.

The burndown chart can be launched from several points, the board and the lanes, and will use the settings defined in the corresponding Estimation to set the start and end date of the sprint (time frame used in x axis). If a report is launched from a lane where information is not set, the information set in the first parent lane, recursively, or board is used. If no date are set, the chart is plotted void. Additionally, the calendar associated to the Easyboards® environment is used to define non-working periods (see Application Settings).

The burndown chart uses the statistical information about the status of cards (see Cards details and settings) and their estimation evaluation (see Cards details and settings) to draw the plotted lines.


Two lines are plotted: the expected trend of work (number of story points remaining in time) and the actual work based on the status of cards.

Due Date Performance

This report shows the capability to respect defined due dates. It is defined as a percentage calculated as the number of cards with Delivery Point date in the period (x-axis point) and with lead time minor or equal to the target lead time divided number of cards with Delivery Point date in the period.

Lead time is the time elapsed between the Delivery Point date time and Commitment Point date time set in the card. This time is calculated considering working hours only if the working calendar is set, see Application Settings for more information.

Data can be plotted by card Priority.

Flow Efficiency

This reports shows the flow efficiency, calculated based on the percentage of working time as defined in the card, see Working Time % in Cards details and settings.

Per each report periot (x-axis point), the average of Working Time % for the cards with Delivery Point date in the period is plotted.

Data can be plotted by card Priority.

Issues

This reports shows the number of work in progress cards and the number of issues in time. Issues are the cards that are blocked.

Work in progress cards in a period (x-axis point) are those with:

  • Work in Progress date within the reporting period or before with no Delivery Point date yet

plus

  • Work in Progress date within the reporting period or before with Delivery Point date in the reporting period or after

Issue cards are those in status blocked and are reported in all the periods including and after the blocking date. The blocking date is defined by the Block command in the card, see Cards commands.

Data can be plotted by card Priority.

Lead Time

Lead time is the time elapsed between the Delivery Point date time and Commitment Point date time set in the card. This time is calculated considering working hours only if the working calendar is set, see Working Calendar for more information.

In the report:

  • a dot is printed per period (x-axis point), being the average lead time of all the cards completed (Delivery Point in the period) in that period; cards considered shall also have Commitment Point and Delivery Point between selected report start and end date;
  • a dot is printed for each selected card Priority;
  • if targets Lead Time are defined, the corresponding defined values are reported in the report. See board command Target, in Board commands.

Data can be plotted by card Priority.

Progress View

This report shows the capability to respect defined due dates. It is defined as a percentage calculated as the number of cards with Delivery Point date in the period (x-axis point) and with lead time minor or equal to the target lead time divided number of cards with Delivery Point date in the period.

Lead time is the time elapsed between the Delivery Point date time and Commitment Point date time set in the card. This time is calculated considering working hours only if the working calendar is set, see Application Settings for more information.

Data can be plotted by card Priority.

Quality

Qaulity report shows the number of cards with defects. This is based on Defective information in the card. The report plots per each period (x-axis point) the number of cards with Delivery Point in the period and Defective value true.

Data can be plotted by card Priority.

Throughput

Throughput is the number of cards completed in a period (Delivery Point in the period, x-axis points). Additionally, the cards considered in a a period are those with Commitment Point date within the reporting period, determined by the selection of report start and end date.

Data can be plotted by card Priority.

Velocity

This report shows the capability to respect defined due dates. It is defined as a percentage calculated as the number of cards with Delivery Point date in the period (x-axis point) and with lead time minor or equal to the target lead time divided number of cards with Delivery Point date in the period.

Lead time is the time elapsed between the Delivery Point date time and Commitment Point date time set in the card. This time is calculated considering working hours only if the working calendar is set, see Application Settings for more information.

Data can be plotted by card Priority.

Work in Progress

This report shows the Work in Progress for the board. It briefly shows the cumulative trends of committed (work that has to be done) and delivered (work completed) cards. The difference is the work in progress that, in a Kanban system, should be limited and controlled.

In a period, x-axis point, the cumulative number of cards with Commitment Point in the period or before (if not delivered) and the cumulative number of cards with Delivery Point in the period on top of the previous are plotted.

Data can be plotted filtering by card Priority.